Construction challenges for this design/build project included a critical time factor. Soil conditions limited the choices, for heavy systems were more than the soil could bear economically, providing even more challenge. Five levels were needed, yet code restrictions limited wood framing to just three.
The solution: Light gauge steel framing; non-combustible, capable of supporting the building's five levels, weighed substantially less than other systems, and could be fabricated and erected quickly.
Midwest Drywall was an early partner in the design process. Shop fabrication was the key to meeting the 10 month schedule. Using two four-man crews, Midwest handled panelization and on-site erection simultaneously. The steel frame was in place three weeks ahead of schedule and 60% complete in just three months. Midwest panelized steel framing provided the solution for on-time completion. |